Contract 26934 REL 6: 200739600 EXP WALLA2 BASIN PASSAGE M&E
Project Number:
Title:
Walla Walla Basinwide Tributary Passage and Flow
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Walla Walla 100.00%
Contract Number:
26934 REL 6
Contract Title:
200739600 EXP WALLA2 BASIN PASSAGE M&E
Contract Continuation:
Previous: Next:
652 REL 34: 199601100 EXP WALLA WALLA FISH PASSAGE M&E
  • 26934 REL 17: 2007-396-00 EXP WALLA WALLA BASIN PASSAGE M&E
Contract Status:
Closed
Contract Description:
2007 Walla Walla Fish Passage Evaluation Project
April 9, 2007 - April 8, 2008

This project was established to provide an evaluation of fish passage facilities and proposed operational or design changes to enhance protection of juvenile salmonids at those facilities in the Walla Walla River Basin, in Oregon and Washington.  The evaluations are guided by provisions of Council Measure 7.11 (NPPC 1994) which follows from previous Council Measures [Section 800 (NPPC 1987) and Section 900 (NPPC 1984)].  The evaluations are funded by the Bonneville Power Administration (BPA) to ensure fish passage facilities "correct structural problems at irrigation diversion dams, canals and ditches that interfere with the passage of anadromous fish" [Council Measure 7.11 (NPPC 1994)].  

CONTRACT GOAL: During the period of performance of this contract (April 9, 2007 through April 8, 2008), Pacific Northwest National Laboratory (PNNL) staff will determine whether new and existing fish passage facilities in the Walla Walla River basin are designed, operated and maintained to be in compliance with NOAA Fisheries fish protection criteria . PNNL's approach to evaluating these sites is discussed briefly in the Approach section.  Specifically,  the new Hofer Dam fish screen will be evaluated as soon as it starts up, probably in April 2007.   If changes are made at Nursery Bridge that could affect flow through the fish screen portion of that facility, it will also be evaluated.  PNNL will also be available to provide technical assistance if requested by Brian Wolcott, the Walla Walla Watershed Council or other tasks under project 2007-396-00 if they identify problems that may impact fish passage within the basin.  

KEY PERSONNEL:  Mickie Chamness will manage this task.  The key field staff is Cherilynn Tunnicliffe.

BACKGROUND INFORMATION:  A large number of fish screen facilities in the Columbia Basin have been constructed with funding from the BPA.  PNNL has been contracted to evaluate fish passage facilities in the Walla Walla Basin immediately after construction to determine if the facilities are designed, constructed, and operated to protect juvenile salmonids.   This determination is based on draft design criteria for juvenile fish screens established by the National Marine Fisheries Service in 1995 (NMFS 1995).  This helps ensure that the investments in construction and maintenance of fish screening facilities are providing adequate protection for migrating fishes,

APPROACH:  A streamlined evaluation process has been developed during the 22 years PNNL has been evaluating Phase I and Phase II fish screen facilities in the Yakima and Walla Walla river basins (Chamness 2006).  That process utilizes field water velocity measurements and compares them to National Marine Fisheries Service draft design criteria for juvenile fish screens (NMFS 1995) to determine if the sites protect juvenile salmonids.  In addition, the process utilizes visual observations and underwater videography to identify fish species, monitor fish behavior, document sedimentation and debris buildup, and identify problems with screen or seal material and general maintenance and operations.
  
COORDINATION OF ACTIVITIES:  For the field evaluation task we will work primarily with the Walla Walla Basin Watershed Council personnel, Confederated Tribe of the Umatilla Reservation, Washington Department of Fish & Wildlife, and the Oregon Department of Fish and Wildlife.  Our work will also require coordination with irrigation districts.  

TECHNICAL REFERENCES:
Chamness, MA.  2006.  Walla Walla River Basin Fish Screens Evaluations:  Nursery Bridge Fishway and Garden City/Lowden II Sites.  DOE/BP-00000652-34, prepared by Pacific Northwest National Laboratory for the Division of Fish and Wildlife, Bonneville Power Administration, Portland, Oregon.

Northwest Power Planning Council (NPPC). 1984.  Columbia River Basin Fish and Wildlife Program.  Northwest Power Planning Council, Portland, Oregon.

Northwest Power Planning Council (NPPC). 1987.  Columbia River Basin Fish and Wildlife Program.  Northwest Power Planning Council, Portland, Oregon.

Northwest Power Planning Council (NPPC). 1994.  Columbia River Basin Fish and Wildlife Program.  Northwest Power Planning Council, Portland, Oregon.

Vucelick J and G McMichael.  2003.  Walla Walla River Basin Fish Screen Evaluations – Nursery Bridge Fishway and Garden City/Lowden II Sites – 2003 Annual Report.  DOE/BP-00000652-15, prepared by Pacific Northwest National Laboratory for the Division of Fish and Wildlife, Bonneville Power Administration, Portland, Oregon.

Vucelick J and G McMichael.  2004.  Walla Walla River Basin Fish Screen Evaluation – Nursery Bridge Fishway, Garden City/Lowden II, and Little Walla Walla Sites – 2004 Annual Report.  DOE/BP 00000652-20, prepared by Pacific Northwest National Laboratory for the Division of Fish and Wildlife, Bonneville Power Administration, Portland, Oregon.
Account Type(s):
Expense
Contract Start Date:
04/09/2007
Contract End Date:
08/31/2008
Current Contract Value:
$17,114
Expenditures:
$17,114

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Funding Package - Submit draft to COTR B: 119. Coordinate and manage work 08/15/2008 06/30/2008
Complete Hofer Dam evaluation C: 157. Evaluate Hofer Dam 07/04/2008 06/04/2008
Submit letter report on Hofer Dam results D: 141. Submit letter report on Hofer Dam results 08/29/2008 08/29/2008
Provide technical assistance/evaluations as requested E: 157. Evaluate other fish screen sites as requested 07/04/2008 07/04/2008
Final report for 2007 uploaded to the BPA website F: 132. Submit annual report on results of any other field work 08/29/2008 08/29/2008
Documentation and assistance to support BPA's Environmental Compliance Group G: 165. Ensure project has necessary environmental clearances 04/08/2008 04/08/2008

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 2 instances of WE 157 Collect/Generate/Validate Field and Lab Data
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 2 instances of WE 157 Collect/Generate/Validate Field and Lab Data
Trout, Bull (S. confluentus) (Threatened)
  • 2 instances of WE 157 Collect/Generate/Validate Field and Lab Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 02/09/2007
B 119 Coordinate and manage work 02/09/2007
C 157 Evaluate Hofer Dam 02/09/2007
D 141 Submit letter report on Hofer Dam results 02/09/2007
E 157 Evaluate other fish screen sites as requested 02/09/2007
F 132 Submit annual report on results of any other field work 02/09/2007
G 165 Ensure project has necessary environmental clearances 02/09/2007